APPLICATION
								
	PREPARATION of the MORTAR  
	- 
		Ensure that the mixture ratio of cement and water for the concrete that shall be added with SUTOP® B-21 is less than 0.55.
- 
		Thoroughly mix SUTOP® B-21 before using.
- 
		Application time is approximately 45 minutes after being added to concrete.
- 
		When type II and III type of Portland cement is used, it is advisable to use setting retarder.
- 
		Conformity tests shall be performed before use.
- 
		Crystallization may occur if SUTOP® B-21 is stored below +8 ºC. The material can be re-used after mixing and homogenizing.
CONSUMPTION
	For concretes to be insulated using SUTOP® B-21
	With a ratio of 2% of the cement amount if Water/cement ratio (w/c) ≤ 0.45
	With a ratio of 2.5% of the cement amount if 0.45 < Water/cement ratio (w/c) ≤ 0.50
	With a ratio of 3% of the cement amount if 0.50 < Water/cement ratio (w/c) ≤ 0.55
	For concretes with Water/cement ratio (w/c) ≥ 0.55; water insulation with SUTOP® B-21 is not suitable. 
	Dosing at concrete plant: 
	SUTOP® B-21 may be added to the mixture with the mixture water as the final component. 
	Dosing at construction site: 
	SUTOP® B-21 is added to the mixer at a ratio of 2-3% and mixed for 3-5 minutes. Mixing shall be performed without delay.